Community News Posted on May 02, 2024

The original article was published from 5/2/2024 12:00:00 AM to 6/30/2030 11:59:00 PM

Below, find information and updates on VTrans projects that may impact Milton traffic. 


Milton US-7 (Hourglass Project)

Installation of new traffic signals, mast arms, and additional lanes on US7. New Alignments and additional lanes on Middle Road and Railroad Street. 

The Railroad Street/Middle Road intersection is currently a three way stop controlled intersection.  This intersection reconfiguration project proposes removing the existing Middle Road and Railroad Street intersections with US-7 and constructing a new access road from Railroad Street to US-7. Visit the Project Website for more information.

Construction Updates

Community members can sign up at any time to receive weekly Construction Updates directly in their inbox by filling out this form.

Latest Update - September 11, 2026

TRAFFIC UPDATES: Keelty Crossing will remain closed. Drivers can expect flagged traffic and short delays within the project area.

hourglass update 09.11.2026

CONSTRUCTION ACTIVITIES: Through next week, the contractor will continue sidewalk installation within the project limits, place topsoil, and install conduit in off-roadway areas. Plants will be delivered early next week, with planting scheduled for later in the week. 

Previous Updates

Contact Information

Contact VTrans with any questions on this project. Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

VTrans Project Manager
Patricia Coburn
(802) 224-6667
patti.coburn@vermont.gov

VTrans Resident Engineer
Christopher Lavalette
(802) 371-9797
chris.lavalette@vermont.gov




Colchester Exit 17 Bridge

Project is for improvements to the US Route 2 and US Route 7 intersection and the US Route 2 and Interstate 89 Exit 17 intersections. Project also includes bridge replacement and corresponding roadway improvements.

The scope of this project includes reconstruction of the bridge structure off-alignment to the north of the existing bridge, reconfiguration of the southbound interchange ramps, modification of the existing northbound off-ramp, reconstruction of all three signalized intersections through the project, and roadway widening to accommodate additional turning lanes at the Chimney Corners Intersection. The Colchester Exit 17 Project was developed in part to address safety concerns that traffic on the northbound off-ramp may back up onto the high-speed travel way of the interstate during peak hours and due to the deteriorating condition of the US Route 2 Bridge over I-89. This project also addresses inefficiencies in traffic patterns at the US Route 2 and US Route 7 intersection (Chimney Corners) and at the I-89 southbound on-ramp. View the Project Fact Sheet

Construction Updates

Visit the Project Website, which is updated regularly with information regarding upcoming construction activities and traffic impacts. Community members can sign up at any time to receive weekly Construction Updates directly in their inbox by filling out this form.

Contact Information

Contact VTrans with any questions on this project. Please note: Contractors are to direct all inquiries to Contract Administration during project advertisement.

Public Information Consultant
Exit 17 Project Information Team
(802) 595-4399