Lake Road Culvert

Lake Road Culvert 09.17.19

Project Overview

Update 11/7/19 - The culvert replacement and paving is complete! Lake Road between Everest Road and Stone Bridge Road will be open to traffic by end of day, November 8.

Cost & Funding

Project Costs

  • Contractor Don Weston: $212,323.00
  • Engineer Trudell Consulting Engineers (TCE): $28,100.00
  • Camp Precast: $65,655.00
  • Larry's Tree Removal: $1,500.00
  • Total Project Cost: $307,578.00

Funding Sources: Bridge & Road Reconstruction Bond

Traffic Impacts

Expected Start Date: September 17th, 2019

Projected Completion Date: Late October, 2019